AWG-1 Production Platform and Wellhead Deck
The EPCI project scope contains the gas production platform, 24-person accommodation module, helideck, vent/microwave tower, bridge and 12 slot wellhead deck. Because of the local waterdepth of 6 metres the production platform was designed as a jack-up barge with a 'De Long' jacking system. The wellhead deck was installed by Taklift 1.
- LocationAWG-1, Ameland, Dutch North Sea
- DimensionsProduction platform 45x25x22 metres
Wellhead deck 22x9x10 metres
Microwave tower 64 metres - WeightProduction platform 4100 tonnes
Wellhead deck 500 tonnes
- Contract AwardMay 1984
- CompletionAugust 1985 (installation)
Januari 1986 (production start-up) - ContractEPCI + Hook-up
- ClientNAM